A Year After St Jude Handover, Still No Date for Full Opening

More than a year after the ceremonial handover of St Jude Hospital, the facility is still awaiting full commissioning, with Prime Minister Philip J. Pierre acknowledging public frustration but offering no clear opening date. The November 16, 2025 ceremony in Vieux Fort marked the completion of construction and the hospital’s handover to the government. At […] The post A Year After St Jude Handover, Still No Date for Full Opening appeared first on Saint Lucia Daily Post.

A Year After St Jude Handover, Still No Date for Full Opening

More than a year after the ceremonial handover of St Jude Hospital, the facility is still awaiting full commissioning, with Prime Minister Philip J. Pierre acknowledging public frustration but offering no clear opening date.

The November 16, 2025 ceremony in Vieux Fort marked the completion of construction and the hospital’s handover to the government. At the time, officials said commissioning would follow to ensure the necessary procedures, equipment and systems were ready for patient care.

Now, Pierre says technical checks must still be completed before the hospital can become fully operational.

“You cannot make a mistake in an HVAC system,” he said, referring to the hospital’s heating, ventilation and air conditioning system. We want to ensure that all the tests and the necessary procedures are taken before the hospital is fully commissioned.”

Responding to questions about the continued delay, Pierre said the building was complete, but unforeseen circumstances had affected the commissioning process. He said the government was following professional advice and would take no chances. The Prime Minister acknowledged that the wait had exceeded his administration’s own expectations.

“It has taken some time. We agree. We understand. We even understand the frustration. We understand it. We too are frustrated,” he said.

Pierre appealed for patience and understanding, assuring the public that St Jude Hospital would be fully commissioned “at the earliest possible time.”

However, he provided no date for the full opening or a timetable for completing the outstanding requirements.

The post A Year After St Jude Handover, Still No Date for Full Opening appeared first on Saint Lucia Daily Post.